HomeSUPPORT QUESTIONS

Need help with StresStimulus? Start here.

Load test runs longer than expected Messages in this topic - RSS

Unregistered User
Unregistered User
Posts: 514


4/17/2017
Unregistered User
Unregistered User
Posts: 514
I setup the load test for 10 minutes, but it executes continuously after 10 minutes. After I click stop, it still cannot stop and generate report. I am sure the port is working and the agent can collect data.
0 link
George @StresStimulus
George @StresStimulus
Administrator
Posts: 566


4/17/2017
George @StresStimulus
George @StresStimulus
Administrator
Posts: 566
The test duration is determined by a two-step algorithm described here http://support.stresstimulus.com/display/doc46/Test-Duration

After 10 minutes, your test continues to run because there are some pending requests have not completed. If you want to stop the test after 10 minutes without waiting for started iterations to complete, then set the property “after the time elapsed “ to “stop the test”, as described here http://support.stresstimulus.com/display/doc46/Run+Duration

Also, after test stops and displays the green wait icon, it needs some time to save the data and complete calculations. Your test is pretty sizable and renders more than 980k requests, so you may take a few steps to configure the test result storage more optimally as described here http://support.stresstimulus.com/display/doc46/Test+Result+Storage

For example, set “purge request/response bodies” to “non-errors”. Or set “how much data to store” to Partial. Or use full SQL Server instead of SQL CE.
0 link






Copyright © 2024 Stimulus Technology